Mold Trials (T1, T2, T3): What Happens & What Buyers Must Verify
A T1 mold trial is a diagnostic steel test, never a finished-part delivery. Buyers who expect spotless, print-compliant parts out of T1 either pressure their molder into hiding steel defects behind extreme press settings—or worse, reject a good toolmaker prematurely. Conversely, treating T1 as a black box where “10 samples arrive in a box” lets gate, venting, and balance flaws slip past the cheap-change window.
1. Trial Sequence: T0 vs T1 vs T2 vs T3
| Trial Stage | Purpose & Tool Readiness | Minimum Shots | Key Deliverable to Buyer |
|---|---|---|---|
| T0 (Dry-Cycle / Toolmaker Test) | Internal shop check before buyer notification: clamp fit, water pressure test (6–8 bar), slide/lifter stroke, ejection travel | 5–15 shots (often unpolished cavity) | Internal leak-free mechanical clearance (usually not shipped) |
| T1 (First Official Trial) | Run in the exact production-grade resin (dried to datasheet) to verify fill balance, ejection, parting line, and baseline shrinkage | 20–50 consecutive shots (after thermal equilibrium) | T1 tagged samples by cavity + Dimensional CMM report (5 pcs/cav) + T1 Defect Action List |
| T2 (Optimization & Process Lock) | Verify T1 steel corrections (gate enlargement, vent grinding, steel-safe grooming) and establish scientific molding window | 30–100 consecutive shots (stable run) | Full FAI dimensional report, 6-step process sheet, and signed cosmetic limit samples |
| T3 / Production Pilot (Run-at-Rate) | Final validation at full quoted cycle time (±5%) on the actual production press (not a tryout-bay press) | 300–1,000+ parts (2–4 hours continuous) | Short-term Cpk ≥ 1.33 on CTQs + cycle-time verification + PPAP/OQ sign-off |
Notice the distinction on T3 / Run-at-Rate: many molders run T1 and T2 in a pampered toolroom tryout press at slow cycle times (e.g., 45 seconds instead of the quoted 28 seconds) to make parts look flat. Never approve final tooling payment until you verify parts run at the quoted production cycle time.
2. Pre-Trial Readiness Checklist (What Ruins a T1 Before Shot #1)
Half of “bad T1 results” come from rushed preparation rather than bad steel. Require photo or log proof of four checks before the first pellet enters the barrel:
- Resin Lot & Desiccant Drying Log: Hygroscopic resins (PA6/PA66, PC, PBT, PET) must dry to datasheet moisture targets (
e.g., PC ≤ 0.02%,PA66 ≤ 0.15%,-40 °Cdew point for3–4 hours). Running undried pellets causes splay streaks and brittle impact failures that waste an entire trial day. - Cooling Flow & Pressure Drop Check: Verify every water circuit holds
6–8 bar(85–115 psi) for 15 minutes with zero leaks, and confirm flow meters reach turbulent flow (≥ 4–6 L/minper circuit) rather than stagnant trickles. - Blue-Spotting Shut-Off Verification: Check Prussian blue transfer on parting lines, slides, and lifters (
≥ 85–90%uniform contact) so the first shot does not flash and peen over delicate venting lands. - Mold Thermal Stabilization: Discard the first
10–15warm-up shots. Steel temperature must stabilize at target (e.g., 60 °Cor85 °C) before collecting T1 measurement samples—cold-tool shots shrink0.15–0.30%differently than steady-state production parts.
3. Reading T1 Samples: What They Prove vs What They Hide
| What T1 Reliably Exposes | What T1 Cannot Prove |
|---|---|
| Incomplete fill / short shots and air-trap burn locations | Long-term dimensional drift over a 4-hour continuous run |
Cavity-to-cavity fill imbalance (>2% weight delta) | True cycle time (tryout technicians routinely run 20–30% slower) |
| Actual weld-line positions, gate blush, and ejector pin distortion | Fatigue life of living hinges or 1,000,000-cycle slide wear |
Baseline linear mold shrinkage (steel-safe grooming targets) | Moisture-conditioned dimensions (test PA6/PA66 both DAM and conditioned) |
Watch Out for “Trial Heroics” (T1 Red Flags)
If T1 samples look unusually glossy and flash-free on a tricky part, inspect the T1 Process Record immediately. Red flags that a technician masked steel flaws with unsustainable press extremes include:
- Barrel melt temperature
15–25 °Cabove the resin supplier’s maximum (causes polymer degradation and long-term field cracking just to fill a thin gate); - Packing pressure
> 90%of machine limit or clamp tonnage maxed out (leaves zero production window); - Use of silicone aerosol mold-release spray to pull sticking parts (silicone ruins downstream pad printing, ultrasonic welding, and medical biocompatibility).
4. Structuring the T1 → T2 Steel-Correction Loop
Keep the T1 correction loop disciplined:
- Measure
3 to 5parts per cavity after16–40 hoursof post-mold stabilization at23 °C / 50% RH(ISO 291). - Group every out-of-spec dimension into Steel-Safe Fixes (removing metal—e.g., enlarging an undersized pin or opening a tight wall—fast,
2–4 days) vs Welding Fixes (adding metal back—slow,7–14 days, risks hardness drops on textured Class A faces). - Require only one parameter variable changed per T2 verification step, logged on the updated setup sheet, before approving First Article Inspection (FAI).
Trial-Day Questions Buyers Should Ask
How many T1/T2 loops should a typical injection mold take?
For a well-reviewed DFM design, two trials (T1 diagnostic + T2 verification) are standard before FAI/PPAP sign-off. If a mold reaches T3 or T4 with persistent dimensional shifts or flash, stop adding minor process tweaks—audit the mold’s cooling layout, platen deflection, or runner balance.
Should the buyer attend T1 in person or via video?
For single-cavity simple parts under $15,000, a video + tagged sample box + CMM report is sufficient. For multi-cavity (≥4 cav) tools, 2K rotary molds, or Class A medical/automotive parts, attend T2 or Run-at-Rate live so you can verify actual cycle time, automated robot degating, and alarm limits on the press screen.
When should the final tooling milestone payment be released?
Never tie final tooling payment (typically 20–30% holdback) to “T1 samples shipped.” Tie it strictly to signed FAI approval + stable T2/Run-at-Rate capability (Cpk ≥ 1.33 on CTQs) + delivery of the 3D mold CAD, steel certs, and master setup sheet.
Disclaimer
PlasticsTechnologyAlliance.com is an independent buyer resource and does not witness mold trials or certify tooling. Define exact T1/T2 sample counts, measurement planes, and payment milestones in your tooling contract before kickoff.
Sources and references
- Injection Mold Trial Process: T0, T1, T2 Step-by-StepMoldMinds
- Scientific Molding: Process Development & Supplier QualificationFictiv
- Scientific Processing & Molding Area Diagram ResourcesFimmTech
Figures quoted from these sources are reproduced as published. Where this guide describes a range or a rule of thumb without a citation, treat it as general orientation and confirm the number against your own part, resin, and supplier. Corrections: [email protected].
Make sure your RFQ package is complete before contacting suppliers
- CAD / STEP file with current revision
- Material selection or approved alternatives
- Annual volume and tooling expectations
- Quality documentation requirements (FAI, PPAP, inspection plan)
- Supplier comparison criteria beyond unit price