T1 Sample Review Checklist: 15-Point Worksheet & Go/Hold Rules
Opening a FedEx box of T1 parts without the supplier’s trial data sheet is a waste of engineering time. Visually inspecting 10 untagged parts tells you what a single shot looked like—not which cavity made it, how hot the technician ran the barrel, or whether the cycle time was 20% slower than quoted.
Work through this worksheet alongside your physical samples, 2D print, and the interactive T1 Review Assistant.
1. Six Mandatory Documents (Before Touching the Parts)
Put the review on immediate hold until the molder sends these six records:
- Trial Metadata Header: Tool ID, T-stage (
T1/T2), date, press tonnage (e.g., 180T), and active cavity count (e.g., 4 of 4). - Cavity-Tagged Sample Set: Minimum
5 consecutive shots per cavitycollected after discarding the first10–15warm-up shots, bagged separately by cavity number. - Master Process Record: Actual measured melt temp (
°C), mold water temp (°C), fill time (s), pack/hold pressure (bar), cushion (3–6 mm), and total cycle time (s). - CMM / Dimensional Report: Measured values for all Critical-to-Quality (
CTQ) dimensions across3–5parts per cavity after16–40 hoursat23 ± 2 °C / 50% RH(ISO 291). - Resin Certificate of Analysis (CoA) & Drying Log: Confirms exact datasheet grade (not a “similar substitute”) and moisture target (
e.g., ≤ 0.02%for PC). - Supplier’s Own Defect & Action List: Toolmaker’s proposed steel corrections (gate open, vent depth, ejector pin trim) with target dates.
2. Cavity-by-Cavity Visual & Functional Audit
Inspect every cavity under 800–1,200 lux diffused daylight at 450–600 mm, logging findings into your Defect Log:
- Shot Weight Balance (
±1.5%): Weigh5degated parts per cavity on a0.01 gscale. Any cavity deviating by> 1.5–2.0%signals runner imbalance or blocked venting. - Short Shots / Unfilled Ribs: Check deep thin ribs (
< 1.0 mm), boss tips, and corners farthest from the gate. - Parting-Line & Slide Flash (
≤ 0.05 mm): Run a fingernail and feeler gauge around parting lines, lifter seams, and ejector pin rings. (Simultaneous short shot + flash indicates platen deflection or localized steel mismatch). - Sink Marks (
≤ 0.03–0.05 mm): Tilt glossy Class A faces at45°under grazing light directly opposite internal ribs and screw bosses. - Weld Lines & Structural Load: Locate knit lines around bosses and cutouts; flex or torque-test any loaded hole (
weld lines typically retain only 50–85% of base tensile strength). - Splay / Silver Streaks & Gas Burns: Check around gates (
shear splay) and end-of-fill blind corners (diesel-effect burn marks). - Gate Vestige & Blush: Measure sub-gate or edge-gate protrusion (
typically ≤ 0.15 mm); check for white stress halos or micro-cracks. - Ejection & Drag Marks: Check tall vertical walls (
draft < 1.0°) for vertical scraping streaks and verify ejector pin witness depth (±0.10 mm). - Mating Assembly Check: Snap or bolt T1 parts into real mating hardware—never rely solely on isolated CMM coordinates to judge fit.
3. T1 Decision Matrix: Approve vs Conditional T2 vs Hold
| T1 Outcome Category | Trigger Condition | Required Next Step |
|---|---|---|
Approve (Rare at T1) | 100% CTQ dimensions in tolerance, zero structural/Class A defects, cycle time within ±5% of quote, full setup sheet delivered | Proceed directly to FAI / Run-at-Rate (300+ pcs) |
| Conditional / Proceed to T2 | Only steel-safe fixes needed (open gate +0.2 mm, deepen vents to 0.025 mm, skim oversized boss pin) + minor dimensional tuning | Authorize T2 steel cut (3–7 days); hold final tool payment |
| HARD HOLD (Stop) | Structural cracks, >10% cycle-time shortfall, continuous mold-release spray needed, wrong resin grade substituted, or missing process sheet | Escalate to supplier engineering lead; demand corrective DFM plan before T2 |
Review FAQs
Why must T1 parts sit 16–40 hours before dimensional inspection?
Semi-crystalline resins (PP, POM, PA6/PA66, PBT) continue post-mold crystallization shrinkage by 0.2–0.6% over the first 24 hours after ejection. Measuring parts straight out of the press (at 45 °C) makes a 100 mm POM gear read 0.35 mm larger than it will measure two days later at your customer’s receiving dock.
What if T1 samples look good, but the supplier won’t share the process setup sheet?
Treat missing process sheets as a hard hold. Without fill time, melt temperature, packing pressure, and cycle seconds, you have no proof the samples were not molded at a 45-second slow cycle or 25 °C over-temp just to pass visual inspection.
Disclaimer
PlasticsTechnologyAlliance.com is an independent buyer resource and does not perform dimensional inspections or witness mold trials. Confirm exact T1 sample counts, stabilization conditions, and holdback criteria in your tooling contract.
Sources and references
- Injection Mold Trial Process: T1 Sample & Documentation StandardsMoldMinds
- ISO 291:2008 — Plastics Standard Atmospheres for Conditioning and TestingISO
- Scientific Molding Process Sheet Requirements at TrialFimmTech
Figures quoted from these sources are reproduced as published. Where this guide describes a range or a rule of thumb without a citation, treat it as general orientation and confirm the number against your own part, resin, and supplier. Corrections: [email protected].
Make sure your RFQ package is complete before contacting suppliers
- CAD / STEP file with current revision
- Material selection or approved alternatives
- Annual volume and tooling expectations
- Quality documentation requirements (FAI, PPAP, inspection plan)
- Supplier comparison criteria beyond unit price